The ground works necessary to install a Skystream wind turbine are not complicated however it is vital that preparation is conducted in accordance to the load requirements. Solar PUmping Solutions can arrange your site preparation using local tradesmen and expert advice according to a pre-supplied quote.
The groundworks should be completed two-three weeks before the installation and commissioning if the turbine itself, so the concrete has time to harden. The subsequent erection, connection and commissioning of the wind turbine should only take a day.
The photos below show the main stages a wind turbine installer takes to install a Skystream wind turbine once the groundworks have been completed.